Water work news!
From Mike Garlock, President of the Board PWSD #1 -- The Gasconade County Public Water Supply District (PWSD) #1 has oversight from the Missouri Department of Natural Resources (DNR). That oversight includes Peaceful Valley water and sewer systems. In a recent inspection, the DNR indicated that our water tower was in need of refurbishment. Our Operations Manager, Don Burrows, sought out companies that could reliably and efficiently perform the work required by the DNR guidelines. There are limited regional companies that perform this type of work and it’s relatively expensive. Bids were sought and the company selected and approved by the PWSD board is Viking Industrial Painting from Omaha, Nebraska.
At a higher level, they will complete the following:
1. Repair / improve various screens,vents, and hardware
2. Remove the interior coating and add coats of primer, epoxy, and sealant to specific areas
3. Fully wash the exterior and apply coats of epoxy and polyurethane
4. Provide a full robotic inspection of the interior and full visual inspection of the exterior in 2028 and prepare an inspection report
The work has already begun, as you see in the picture above, taken March 24. Our water tower was offline at that time. We are now accessing water through alternate means but this should have no impact to water pressure for most, if not all, users. We’ll keep customers notified of any alerts or actions.
The total cost is $113,704 and the work should take approximately 3 weeks to complete. Don was able to secure payment terms that are favorable to the PWSD. Our initial payment is $25,000 and has been provided to Viking. After that, we will have 4 equal payments of $22,176 due on December 1st of 2025 through 2028.
Progress on the Waste Water Treatment Facility
The winning contractor for the new Waste Water Treatment Facility (WWTF) has been selected and will be announced soon. The PWSD will close on the WWTF loan on Apr. 9th and will hold the preconstruction meeting the same day. Construction activity should begin shortly after and is expected to be complete by the end of 2024.